Bonding and liquidated damages: when to walk away

Two clauses kill more public bids than most estimators admit. Here is how to read them before you spend days on a takeoff.

Decision rule

If bonding is above capacity or LD exposure exceeds what your schedule can absorb, treat the RFP as NO-GO until a concrete mitigation path exists — not a hope.

What to scan first

  1. 1

    Bid bond as a capacity filter

    If the bid bond percentage times estimated contract value exceeds what your surety will support this week, stop. Do not start a takeoff hoping the broker “figures it out.”

  2. 2

    Performance and payment bonds

    100% P&P bonds on a project above your single-job limit are a hard NO-GO unless you have a written co-surety or joint-venture path before bid day.

  3. 3

    Liquidated damages vs crew reality

    High daily LDs with an aggressive completion date turn thin-margin work into a loss. Match LD exposure to weather windows, long-lead equipment, and crew availability.

  4. 4

    Addenda that change bond or LD math

    Late addenda often raise bond amounts or compress schedule. Re-run the go/no-go after every material addendum — not only after the first PDF.

Faster path with RFPCheck

RFPCheck flags bonding and liquidated-damages language in the PDF so you can kill bad fits in under a minute. Always verify amounts in the source solicitation.

FAQ

What bonding red flags usually mean NO-GO?

Bid bond above surety comfort, performance/payment bonds above single-project capacity, and no time to structure a joint venture or co-surety before the due date.

Are liquidated damages always a deal-breaker?

No. Modest LDs with a realistic schedule can be fine. Steep daily LDs plus incomplete drawings, owner-caused delay history, or fixed end dates with no float are the dangerous combination.